Project: Cinema
Complex
Location: Birmingham
Completion Date: 2003
Roof finish: metal deck inverted roof /rock wool rigid slab insulation/Single
Ply PVC membrane with Flagstones & aggregate ballast.
Roof-Pro Products: RP custom
Pods / Bi Pods / PF 1 & 2 18x4T / Access Platforms & Steps
18x6TP &12x4T / Tab C 500
Roof -Pro Ltd were brought into this project by a building services consultant who wanted to manage the weight loading on the services installation. During early design stage Roof-Pro conducted a number of engineering assessments determining the static load pressures and Kn/m2
point loadings for the range of heavy building services
equipment which included several 1.5 ton AHU’s.
After consultation of the intended services layout, Roof-Pro designed the most effective support solution. Pod's were fabricated for the AHU's and services positioned directly onto rigid insulation where flagstones
have been removed, something only made possible because of the very low
compressive loads through each foot.
Roof-Pro technical sales managers and technical office went on to work with the D&B design team and main contractors
on other projects where they assisted with on-site technical design support, CAD production drawings
and site surveys to determine appropriate product specifications
to support - AHU’s, condensers, pipes, cables & ducts and bespoke freestanding