Project: Torquay Marina
Car Park.
Product: RedLINE 40.
Traditional car park laid to falls. Consisted of concrete
deck with two layers of asphalt, (30mm paving grade & 20mm
two coat roofing grade laid on a glass fibre tissue-separating
layer.
The joint failed allowing water ingress to the business units
below. Redline was selected for the joint repair as it is able
to continue the waterproofing integrity through complex changes
in direction and is compatible with the existing waterproofing.
Redline can be joined together on site with a portable vulcanising
machine permitting a phased approach to a continuous joint.
 |
 |
 |
 |
| 1. Expansion Joint Overview. |
2. First layer of waterproofing
applied |
3. RedLINE 40 being applied. |
4. Two 90 Degree changes in direction. |
 |
|
|
|
 |
 |
 |
5. Second layer of waterproofing
being applied. |
6. RedLINE 40 encapsulated
between two layers of waterproofing.
|
7. Waterproofing layer applied to
RedLINE 40 dressed up a vertical face. |
| |
|
|
|